Agile Investment - Proof Of Concept (PoC) Checklist

During the PoC Phase:

  • Agile Scrum team is assigned to implement and test solution recommendation
  • Provide and measure outcome of PoC team
  • Review PoC recommendation
  • Business / technical review to approve/reject progressing to next Phase

    Input Checklist Before Starting PoC

Scope and Approach

  • PoC scope is defined
  • High-level business needs have been identified and prioritized
  • High-level technical needs and requirements have been identified and prioritized
  • Approach for PoC phase had been defined

People and Resources

  • Sponsoring Department/Executive has been defined
  • Key personnel resources and skill sets identified and secured
    • Assigned Product Owner from the Business Team
    • Assigned Scrum Master
    • Agile coaching support and guidance
  • Team members are fully dedicated to the PoC effort

Development Environment

  • Development environment setup completed (e.g. test/dev environment, production, etc.)
  • Access requirements identified, requested and setup completed

    PoC Output Checklist

PoC Success Criteria

  • Measures of success for PoC have been met and accepted by stakeholders
  • Recommendation for Prototype phase developed
    • Key personnel resources and skill requirements identified
    • Process approach is defined
  • Prototype Scope is defined
    • High-level business features have been identified and prioritized
    • High-level technical features and requirements have been identified and prioritized

Sample Technical Considerations for Next Phase Recommendations

Existing Solutions and Systems

  • Has it been specified if the solution requested is a feature fix or capability enhancement on an existing platform?
  • Has it been determined if the capability will reside in a solution that is GSA-internal or managed by an external vendor
  • Specify if it will reside on a current GSA IT platform that is up for contract renegotiation
  • Has it been determined if Solution is cloud based, if not, will it need to integrate with an application maintained in Cloud Services or on premise services?

Software

  • Has solution languages, tools and applications been determined e.g. web, mobile, core SW languages (Java, Python), Open source/public code, etc.?
  • Has it been specified if the solution requested is a service or solution IaaS, PaaS or SaaS?

Data

  • Has the type of data the solution will work with been identified? (e.g. No Data, Structured Data OR/AND Unstructured Data)
  • Has the condition of the data been specified (Format - JSON, XML, Excel, CSV, etc. Data size, frequency of capture, current storage)?

Security

  • Has it been determined if PII or Payment Card Information (e.g. credit card numbers) will be stored in the system?
  • Has it been stated if the solution should leverage Single Sign-on (SSO). If yes, have the applicable GSA IT platforms or applications identified?

Environment and Integration

  • Has the list of other applications the solution requires to interface/integrate with been identified? (e.g. GSA IT platforms, Vendor platforms, etc.)
  • Have integration requirements with a third-party application, another system within GSA, and/or a system outside GSA? If yes, have applications been listed?

Network

  • Specify if the system is assessed through GSA network only or through outside network
  • Has required access been identified, requested and setup completed?